Project Construction Schedule

Lee Kennedy Company of Quincy, MA has been engaged as the Construction Manager for the 160 Massachusetts Avenue project. Following is the anticipated schedule of major project milestones:

Description Date
Site Clearance September – October 2011
Ground Breaking Ceremony November 30, 2011
Support of Excavation and Site-work December 2011 – March 2012
Foundations March – May 2012
Structural steel and deck June – November 2012
Exterior Wall Construction September 2012 – February 2013
Substantial Completion July 2013
Final Completion August 2013

Look-ahead schedule (construction activity in the coming two weeks)

Week of 4/6/2013 - 4/13/2013
Install elevators
Prep. Podium curtainwall
Installing Curtain wall Podium north west, will require Saturday work.
Interior LGMF floors B1-B2
Interior LGMF floors 5 thru 16
Sheetrock/finishes B1,B2 - 5 thru 16
Mechanical rough in B2 - MPH
Material Load in, will require Saturday work.
Week of 4/14/2013 - 4/20/2013
Install elevators
Installing Curtain wall Podium north west, will require Saturday work.
Interior LGMF floors B1-B2
Interior LGMF floors 5 thru 16
Sheetrock/finishes B1,B2 - 5 thru 16
Mechanical rough in B2 - MPH
Material Load in, will require Saturday work.