Lee Kennedy Company of Quincy, MA has been engaged as the Construction Manager for the 160 Massachusetts Avenue project. Following is the anticipated schedule of major project milestones:
| Site Clearance |
September – October 2011 |
| Ground Breaking Ceremony |
November 30, 2011 |
| Support of Excavation and Site-work |
December 2011 – March 2012 |
| Foundations |
March – May 2012 |
| Structural steel and deck |
June – November 2012 |
| Exterior Wall Construction |
September 2012 – February 2013 |
| Substantial Completion |
July 2013 |
| Final Completion |
August 2013 |
Look-ahead schedule (construction activity in the coming two weeks)
| Install elevators |
| Prep. Podium curtainwall |
| Installing Curtain wall Podium north west, will require Saturday work. |
| Interior LGMF floors B1-B2 |
| Interior LGMF floors 5 thru 16 |
| Sheetrock/finishes B1,B2 - 5 thru 16 |
| Mechanical rough in B2 - MPH |
| Material Load in, will require Saturday work. |
| Install elevators |
| Installing Curtain wall Podium north west, will require Saturday work. |
| Interior LGMF floors B1-B2 |
| Interior LGMF floors 5 thru 16 |
| Sheetrock/finishes B1,B2 - 5 thru 16 |
| Mechanical rough in B2 - MPH |
| Material Load in, will require Saturday work. |