Project Construction Schedule

Lee Kennedy Company of Quincy, MA has been engaged as the Construction Manager for the 160 Massachusetts Avenue project. Following is the anticipated schedule of major project milestones:

Description Date
Site Clearance September – October 2011
Ground Breaking Ceremony November 30, 2011
Support of Excavation and Site-work December 2011 – March 2012
Foundations March – May 2012
Structural steel and deck June – November 2012
Exterior Wall Construction September 2012 – February 2013
Substantial Completion July 2013
Final Completion August 2013

Look-ahead schedule (construction activity in the coming two weeks)

Week of 6/9/2013 - 6/15/2013
Install elevators.
Installation of Podium Stud Wall panels, will require Saturday and Sunday work to make up schedule.
Installation of 4th floor curtain wall panels, may require Saturday work and long days to make up schedule.
Installation of 5th and 6th floor stud wall panels, may require Saturday work and long days to make up schedule.
Sheetrock/finishes B1, B2 and 5 thru 16.
Mechanical rough in B2 - MPH.
Miscellaneous material load in, prep work for curtain wall installation, will require Saturday work.
Week of 6/16/2013 - 6/22/2013
Install elevators.
Installation of Podium Stud Wall panels, will require Saturday and Sunday work to make up schedule.
Installation of 4th floor curtain wall panels, may require Saturday work and long days to make up schedule.
Installation of 5th and 6th floor stud wall panels, may require Saturday work and long days to make up schedule.
Sheetrock/finishes B1, B2 and 5 thru 16.
Mechanical rough in B2 - MPH.
Miscellaneous material load in, prep work for curtain wall installation, will require Saturday work.